Stockout Cost: Calculate It for a Lost Sale, Backorder or Line Stop

In the worked example below, one item runs out for six days at 40 units a day. The 96 units whose buyers leave cost ₹24,000 in lost contribution, the selling price less the variable cost. The 144 units whose buyers wait cost only ₹3,235, so the same stockout costs ₹27,235 in total, and the share of buyers who leave drives almost all of it. A lost-units-times-profit formula suits a shop counter. It does not cover the order that waits, the late-delivery clause in a supply contract, or a production line that stops for want of one part. In that last case, adding idle wages to lost profit counts the same rupees twice. This page gives you one short calculation for each case, with rupee inputs you can replace with your own. It also shows how to measure the share of customers who leave, and gives a rule for deciding whether extra stock is worth holding. For the definition and causes, see our stockout page.

days
units a day
₹per unit
₹per unit
₹per unit
%
days

Direct cost of the stockout

₹27,235

Units lost
96
Lost-sale cost
₹24,000
Backorder cost (before any penalty)
₹3,235

Assumptions

  • The inputs are assumed values, to be replaced with your own.
  • Selling price excludes GST, because you collect it for the government and would not have kept it.
  • The share of demand lost is a guess until you measure it from your own order log.
  • The multiplier tiers (1.5 and 3.0) are upper scenarios inferred from one consumer study, not measured B2B figures.

By Praveen Nune, Co-Founder & CEO · Updated 19 Nov 2026

In brief

The share of buyers who leave drives almost all of the cost of a stockout. Calculate each case separately: a lost sale costs contribution, a backorder costs handling, financing and any penalty, and a stopped line costs lost output or idle wages, never both.

Worked example at the defaults

With Days without stock at 6days, Daily demand (average on days with stock) at 40units a day, Selling price, excluding GST at ₹1,250per unit, Variable cost (purchase or material cost, inward freight) at ₹1,000per unit, Share of demand lost at 40%, Handling and expediting on backordered units at ₹20per unit, Annual finance rate at 12%, Days payment arrives late at 6days:

Units lost
96
Lost-sale cost
₹24,000
Backorder cost (before any penalty)
₹3,235
Direct cost of the stockout
₹27,235

Lost-sale cost (₹) = days out × daily demand × share lost × (price − variable cost). Backorder cost (₹) = units backordered × handling and expediting per unit + units backordered × price × annual finance rate × days late ÷ 365 + penalty. Units backordered are the units demanded less the units lost. This is standard contribution arithmetic. The calculator leaves out any late-delivery penalty, because it depends on your contract; see the backorder section for the central government rule.

Key takeaways

  • Stockout cost depends on what happens to the order. A lost sale costs contribution (price less variable cost) per unit. A backorder costs handling, financing and any penalty. A stopped line costs lost output or idle wages plus make-up, never both.
  • In our worked example, one item unavailable for six days costs ₹27,235 in direct cost. ₹24,000 of that is the 40% of demand that left, so the share of buyers who leave is the number to measure.
  • As of November 2026, the Manual for Procurement of Goods (Second Edition 2024, para 9.3.9) lets a central government buyer recover 0.5% of the delivered price per week or part of a week. The cap is 5% of contract value by default and 10% for inordinate delay (a delay of more than a quarter of the delivery period). Check your own contract's clause.
  • Add a repeat-order multiplier (1.5 to 3 in our model) only as an upper scenario. It rests on one consumer study.

How do you calculate stockout cost for a lost sale?

Multiply the units customers would have bought by the share who went elsewhere, then by contribution per unit. Contribution per unit is the selling price less the variable cost, meaning the cost that rises with every unit sold. This is standard contribution arithmetic. The inputs below are our assumed values, to be replaced with yours.

Lost-sale cost (₹) = days out × daily demand × share lost × (price − variable cost)

Working: 6 × 40 = 240 units demanded. 40% of 240 = 96 units lost. Contribution is ₹1,250 − ₹1,000 = ₹250 a unit. 96 × ₹250 = ₹24,000.

Read the result as a range, because the share lost is a guess until you measure it. At 20% lost, the cost is 48 units × ₹250 = ₹12,000. At 60%, it is 144 units × ₹250 = ₹36,000. Exclude GST from the price, because you collect it for the government and would not have kept it.

Input
Days without stock
Unit
days
Default used here
6
Input
Daily demand (average on days with stock)
Unit
units a day
Default used here
40
Input
Selling price, excluding Goods and Services Tax (GST)
Unit
₹ per unit
Default used here
1,250
Input
Variable cost (purchase or material cost, inward freight)
Unit
₹ per unit
Default used here
1,000
Input
Share of demand lost
Unit
%
Default used here
40

What does a backorder cost compared with a lost sale?

A backorder usually costs far less in cash than a lost sale, because you still earn the contribution. You pay for handling and expediting (paying extra to speed up a late supply, such as air freight or a premium for urgent delivery), for financing the late receipt of money, and for any late-delivery penalty.

Backorder cost (₹) = units backordered × handling and expediting per unit + units backordered × price × annual finance rate × days late ÷ 365 + penalty

In the example, 144 units are backordered (240 − 96). Assume ₹20 a unit for handling and expediting, a 12% annual finance rate (use your own cash-credit rate, meaning the rate on a bank overdraft-style working-capital limit, or your loan rate) and payment arriving 6 days later.

  • Handling: 144 × ₹20 = ₹2,880.
  • Financing: 144 × ₹1,250 = ₹1,80,000; × 12% × 6 ÷ 365 ≈ ₹355.
  • Total: ₹2,880 + ₹355 = ₹3,235.

Direct cost of the stockout: ₹24,000 + ₹3,235 = ₹27,235.

Penalty. If you supply a central government department, then as of November 2026 the Manual for Procurement of Goods, Second Edition 2024 (Ministry of Finance, Department of Expenditure, para 9.3.9) lets the buyer recover 0.5% of the delivered price of the delayed goods for each week of delay or part of a week. The delivered price includes GST and freight. The cap is 5% of total contract value by default, or 10% for inordinate delay (a delay of more than a quarter of the delivery period). On a ₹20 lakh order delivered 3 weeks late, that is 3 × 0.5% = 1.5%, or ₹30,000. The 5% cap (₹1,00,000) is reached after 10 weeks. This is the manual's rule for central government contracts. Private buyers set their own terms, so read your own contract.

Do not buy patience with a discount. A field test with 22,921 catalogue customers found that offering a discount to get customers to wait was the least profitable of five responses. Telling customers the item was "extremely popular" worked best (Anderson, Fitzsimons and Simester, Management Science, 2006). That was a consumer mail-order business, so treat it as a caution, not a law, for business buyers.

How do you cost a production line that stops for want of one part?

Pick one of two routes. If the lost output is gone for good, the cost is lost contribution plus any expediting. If you make the output up later, it is idle wages plus the make-up premium plus expediting. Adding idle wages to lost contribution counts the same rupees twice. Contribution is measured before fixed costs such as permanent workers' pay, so that pay is already inside it.

  • Output lost for good: hours stopped × units per hour × contribution per unit + expediting.
  • Output made up later: hours stopped × idle workers × wage per hour + make-up hours × workers × overtime premium per hour + expediting.

Illustrative inputs: 6 hours stopped, 25 units an hour, ₹600 contribution a unit, 40 workers at ₹150 an hour, an overtime premium of ₹75 per worker-hour, and ₹12,000 to expedite the part.

Use the second route only if you really can recover the hours, with spare shifts and customers who can wait.

Use the wages you actually pay for the idle hours. Whether a given stoppage counts as a lay-off under labour law is a question for your labour adviser.

Route
Output lost
Working
6 × 25 × ₹600 = ₹90,000, plus ₹12,000
Cost
₹1,02,000
Route
Output made up
Working
40 × ₹150 × 6 = ₹36,000; 40 × ₹75 × 6 = ₹18,000; plus ₹12,000
Cost
₹66,000

Should you add a multiplier for repeat orders and other lines?

Treat a multiplier as an upper scenario, not your base number. In the Anderson, Fitzsimons and Simester field test (2006), a stockout on one item raised cancellations on the other items in the same order. That basket effect was almost 33% of the total short-run cost. The long-run cost, from customers who then ordered less, was almost as large as the short-run cost (Anderson et al., 2006). The authors say the exact size will differ between firms and markets.

Our model turns this into tiers that multiply only the lost-sale cost, because the paper's basket effect is cancellation of other items, which applies to customers who leave, not to those who wait. If the basket effect is 33% of the short-run total, short-run cost is the lost-sale cost ÷ 0.67, about 1.5 times. If the long-run effect roughly equals that, the total is about 3 times. Both steps are our inference from one consumer study, not a measured B2B (business-to-business) figure.

Our recommendation is to decide on the 1.0 figure. Quote the higher tiers only for customers who order several lines or reorder regularly, where losing them would clearly hurt.

Tier
1.0 (base)
Lost-sale part
₹24,000
Backorder part
₹3,235
Total
₹27,235
Tier
1.5 (basket effect)
Lost-sale part
₹36,000
Backorder part
₹3,235
Total
₹39,235
Tier
3.0 (basket plus repeat)
Lost-sale part
₹72,000
Backorder part
₹3,235
Total
₹75,235

How do you find the share of customers who leave?

Log every short order line for 30 days. For each one, record the item, the date, units asked for, units shipped on time, units shipped late with days late, and units cancelled. Then:

Share lost = units cancelled ÷ (units cancelled + units shipped late)

Keep logging until you have at least 20 short lines for the item or product family, because a handful of cases tells you little. Two older consumer surveys cited in Anderson et al. (2006) found that 14% (Emmelhainz et al., 1991) and nearly half (Schary and Christopher, 1979) of shoppers who met a stockout said they planned to buy at another store. These are stated intentions from retail shoppers, not business buyers. Business buyers may behave very differently, which is why your own log beats any default.

Our inventory alerts flag items approaching or falling below minimum stock levels. They also alert users when stock arrives for items under back order, so you know the day a backorder can be filled. Alerts are included from our Basic plan upwards. The cancelled-versus-late split still comes from your order records.

How do you read the result and decide whether to hold more stock?

Compare the cost of one stockout, multiplied by how often it happens in a year, with the yearly cost of the extra stock that would prevent it. If the first is larger, hold more stock or fix the buying. If it is smaller, accept the occasional stockout. The extra stock's yearly cost is its value times your carrying cost rate; our guide to inventory carrying cost in India shows how to build that rate.

Use the base figure (₹27,235 in the example) for the decision. Use the 3.0 tier to test whether the decision survives a pessimistic view. If it only works at 3.0, the evidence for extra stock is weak. Then test whether better demand planning or sharper inventory visibility removes the stockout more cheaply than extra stock does.

As of November 2026, our Basic plan, which includes inventory alerts, costs $199 a month billed annually (pricing). Start the 15-day free trial (full access, no credit card), or book a demo via contact sales.

Keep reading

Frequently asked

There is no single formula, because you cost the shortage by what happened to the order. Use contribution on the units lost, handling, financing and any penalty on the units delayed, and lost output or idle wages on a stopped line. Calculate each case separately, then add the parts that apply to your stockout.
No. Lost sales are only the part of a stockout where the customer leaves, and you cost them at contribution, not at revenue. Orders that wait have separate costs, and a stopped line has its own. The three cases only share a cause, which is the item not being there.
The buyer may recover liquidated damages, a pre-agreed sum for late delivery, for each week of delay under the clause in your contract. For central government contracts, the procurement manual allows 0.5% of the delivered price per week or part of a week, capped at 5% of contract value by default. Read your own contract.
Add nothing to your base figure. Decide on the base lost-sale cost, and test 1.5 and 3 times the lost-sale cost only as pessimistic scenarios. Those multipliers rest on one consumer study, so quote the higher tiers only for customers who order several lines or reorder regularly.

Sources

  1. 1.Anderson, E., Fitzsimons, G. and Simester, D., "Measuring and Mitigating the Costs of Stockouts", Management Science 52(11), November 2006, Management Science, November 2006
  2. 2.Manual for Procurement of Goods, Second Edition 2024 (para 9.3.9, quantum of liquidated damages), Ministry of Finance, Department of Expenditure, Government of India, 2024